top of page

CONSTRUCTION
Florence Cancer Center
Project description:
40000 SF medical complex in Florence Alabama. The general contractor was The Arcon Group.
Project Budget:
As of July 1, 2020 CG Jones has completed 70% of the $1.2 million contract.
Work Preformed:
CG Jones performed demolition, clearing & grubbing, site grading, site drainage, utilities, base & pave, curb & gutter, and sidewalks.

bottom of page